Late September Construction Progress - Building B
1 2 3







Two large cisterns have been
built into the foundation of Building B.









The slab is insulated with Styrofoam to protect both
the water supply and the slab from water damage.










The foundation prior to the concrete pour.










Steel work being done prior to the concrete pour.









The foundation's slab was poured over three days.
First, the stair and veranda slab's were poured,
then came B2's floor, and then B1's floor.











Here is B1's floor being leveled off.