C5 & C6 Construction Progress - October 2006


Milestone

Foundation

Walls

Roof

Windows & Doors

Paint & Tile

Finish Work

Complete

Completion Date

X

Jan 07

Mar 07

April 07

May 07

July 07

Aug 07

% Complete

20%

40%

60%

70%

80%

90%

100%




C5 and C6 will be built on the third floor of Building C,
above C3 and C4, which are pictured here.





The work being done at present above C3 and C4 will
be part of the third floor slab--the floors of C5 and C6.






Here C6's veranda is nearly ready to be poured
.





The verandas of C5 and C6 are offset for the utmost privacy.





Here is a close up of the veranda of C6 just prior to the concrete pour.






Here is the recently poured veranda of C5. The veranda of C6
and the rest of the slab will be poured by early December 2006.



A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6


D1

D2

D3

D4

D5

D6



Back to Construction Progress Chart


Back to Construction Photo Gallery


Back to Main Photo Gallery