B5 Construction Progress - October 2006


Milestone

Foundation

Walls

Roof

Windows & Doors

Paint & Tile

Finish Work

Complete

Completion Date

X

Mar 07

May 07

June 07

July 07

Aug 07

Sept 07

% Complete

20%

40%

60%

70%

80%

90%

100%




B5's layout on the second floor will mimic the layout of B1, pictured here.






Both condos will offer a 510 sq ft wrap around veranda.







This is B1's the sizable living room and kitchen
area, similar to what will be built in B5.






The third floor slab of of Building B will be poured by February 2007. Immediately following the walls of B5 will be started.