Construction Progress - October 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
Jan
07 |
Mar
07 |
May
07 |
June
07 |
July
07 |
Sept
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

B3's layout on the second floor will mimic the layout of B1, pictured
here.
|

Both condos will offer a 510 sq ft wrap around veranda.
|

This
is B1's the sizable living room and kitchen
area, similar to what will be built in B3.
|

The
second floor slab of of Building B will be poured by early December
2006. Immediately following the walls of B3 will be started.
|