Construction Progress - October 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
Dec
06 |
Mar
07 |
May
07 |
July
07 |
Sept
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

Looking down on the floor plan of first floor three bedroom condo
B2.
|

B2 viewed from the steps of Building C.
|

Here is the spacious veranda of B2.
|

The
living room and kitchen area of B2. The entrances
to the two guest bedrooms can be found at back left.
|

The
master bedroom of B2 offers direct access to the veranda.
|

The foundation of Building B was raised up in part to provide
superior views to B1 and B2, the two first floor condos.
|