A5 Construction Progress - October 2006


Milestone

Foundation

Walls

Roof

Windows & Doors

Paint & Tile

Finish Work

Complete

Completion Date

X

X

X

Feb 07

April 07

June 07

Aug 07

% Complete

20%

40%

60%

70%

80%

90%

100%




A5 is the second floor condo pictured here
.





A5's expansive living room and dining area.






The guest bedroom of A5. The walls have been rough plastered. Next,
they will be smooth plastered, and then the drop ceiling will be built.





The Caribbean view looking out from the living room.





Looking out across the 1,115 sq ft private veranda of A5.








The Caribbean view from second floor condo A5.