A3
Construction Progress - October 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
Jan
07 |
Mar
07 |
June
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

A3 is the first floor condo pictured here. The interior tile to
be used throughout Building A's first floor condos is stacked
on its veranda.
|

The 550 sq ft private veranda extends over
10 feet towards the Caribbean, pool, and grounds.
|

The
living room and kitchen area of A3. The
interior walls have
been plastered and the drop ceilings built. Presently our crew
is installing the air conditioning ducting and recessed lights.
|

The
master bedroom of A3 offers a large walk-in closet.
|

A3's
veranda looking towards the Caribbean. The exterior
doors and windows of A3 were installed earlier this month.
|

The expansive Caribbean view from first floor condo A3.
|