Construction Progress - November 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
Dec
06 |
Dec
06 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

The beachfront perspective of building D in late November 2006.
|

D4 is the second floor condo seen here.
|

The
kitchen cabinets have been installed in D4 and
the appliances will be connected by mid December.
|

The granite countertops in D4's kitchen are now complete.
|

The
marble countertop around the
master vanities was recently installed.
|

The
marble surrounding the jacuzzi tub
was also installed in late November.
|

The
master closet provides a large amount of storage in D4.
|

The Caribbean view looking from D4's private veranda.
|