D2
Construction Progress - November 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
X |
Dec
06 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

Building D in late November 2006.
|

First floor condo D2 can be seen at the bottom right of this picture.
|

The
beachfront perspective of Building D of The Phoenix.
|

The private veranda of first floor condo D2.
|

The
veranda offers 355 square feet of private outdoor space.
|

The finished kitchen of first floor condo D2.
|