D2 Construction Progress - November 2006


Milestone

Foundation

Walls

Roof

Windows & Doors

Paint & Tile

Finish Work

Complete

Completion Date

X

X

X

X

X

X

Dec 06

% Complete

20%

40%

60%

70%

80%

90%

100%