Construction Progress - November 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
March
07 |
April
07 |
May
07 |
June
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

The third floor slab of Building C was poured in mid November.
|

C2
is the first floor condo pictured here at right.
|

C2's
spacious living room and kitchen
area look out towards the Caribbean.
|

The walls of the master bedroom have been rough plastered.
|

The
showers in C2 have been redesigned to allow more natural light
in.
|

The two large windows in C2's guest bedroom will bring in a lot
of natural light and allow a brisk cross breeze to pass through.
|