B5
Construction Progress - November 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
Mar
07 |
May
07 |
June
07 |
July
07 |
Aug
07 |
Sept
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

Looking
down on the first floor of Building B.
|

B5 will be built on the third floor above B1.
|

B5
will offer a third floor veranda that
extends 22 feet towards the Caribbean.
|

Like B1 and B3, B5 will offer 1,325 interior square
feet and 510 square feet on its private veranda.
|

Here is the main staircase taking shape that
leads to the second and third floors of Building B.
|

Here
are the beams that will support
the second staircase leading to B5.
|