Construction Progress - November 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
Jan
07 |
Mar
07 |
May
07 |
June
07 |
July
07 |
Sept
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

B4 will be built above the beams shown here.
|

The roof of B2 and floor of B4 will be poured in mid December.
|

B4 will be built directly above B2 and provide a shaded veranda
below.
|