Construction Progress - November 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
Jan
07 |
Mar
07 |
June
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

A2 is the first floor condo located between the main
staircase of Building A and first floor beachfront condo A1.
|

A2's boasts a 550 square foot private veranda. The living room
and both bedrooms of A2 provide private access to this veranda.
|

The
installation of air conditioning ducting
and recessed lights has been completed in A2.
|

Our crew is presently installing plycem througout A2.
|

With
the drop ceilings in A2 nearly complete,
our crew will next begin painting the walls.
|

Building A's first floor back hallway was designed to
allow large amounts of air and light to filter through.
|