A1
Construction Progress - November 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
Dec
06 |
Mar
07 |
June
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

A1's interior walls were recently painted.
|

A1's spacious dining room looks out directly onto the Caribbean.
|

The
kitchen of first floor condo A1.
|

Following
the painting of the interior walls,
the living room of A1 is now being tiled.
|

The
glass block in the guest bathroom will allow natural
light to fliter through the shower and into the larger room.
|

The master bathroom offers a spacious
shower, jacuzzi tub, and his and hers vanities.
|

A1's
master bedroom provides a walk-in closet
and private access to the master bathroom.
|

Building A's first floor rear hallway was recently plastered.
|