C3
Construction Progress - December 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
April
07 |
May
07 |
June
07 |
August
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

C3
is the second floor condo pictured at left.
|

Building
C offers a well lit and breezy hallway on its second floor.
|

C3
will offer a spacious living room and kitchen.
|

Many
of the interior walls of C3 have been rough plastered.
|

C3
offers a 355' private veranda directly facing the Caribbean.
|

Second
floor condo C3 offers this view of the Caribbean.
|