B3
Construction Progress - December 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
Jan
07 |
Mar
07 |
May
07 |
June
07 |
July
07 |
Sept
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

B3 will be built on the left side of the
recently poured second floor slab of Building B.
|

One
bedroom condo B3 offers a spacious living room and kitchen.
|

The bedroom of B3 opens directly onto the condo's wrap around
veranda.
|

The 510 square foot veranda extends 22' towards the Caribbean.
|

Here is the view from the kitchen of B3.
|