Construction Progress - December 2006
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
April
07 |
June
07 |
August
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

A4 is the first floor condo pictured at right.
|

A4's veranda extends 11' towards the Caribbean,
creating a 550 square foot outdoor living area.
|

A4 is presently being used to store
a large amount of construction materials.
|

The
back hallway of Building A's first floor was
designed to be spacious and full of natural light.
|