C5 Construction Progress - September 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

X

X

Oct 07

Dec 07

Dec 07

Jan 08

Feb 08

% Complete

70%

75%

80%

85%

90%

95%

100%

The Phoenix Resort in Belize Condo C5 #1


C5 provides an amazing Caribbean view.


The Phoenix Resort in Belize Condo C5 #2


Here are the living room and kitchen of C5 being painted.





The Phoenix Resort in Belize Condo C5 #3




After the painting was completed our crew prepared for the tile work.




The Phoenix Resort in Belize Condo C5 #4




Here is the living room of C5 being tiled in late September.





The Phoenix Resort in Belize Condo C5 #5




This is the master bedroom of C5 after being painted.






The Phoenix Resort in Belize Condo C5 #6



Here are the early stages of tiling the
master bedroom from late September 2007.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6


The Phoenix Property 1




Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery