Construction Progress - April 2008
| Milestone |
Paint & Tile |
Kitchen
&
BTH Cabinets |
Appliances
& Fixtures |
Wood
Finish Work |
Furniture |
Complete |
|
Completion Date |
X |
X
|
X |
Apr
08 |
Apr
08 |
Apr
08 |
| %
Complete |
75% |
80% |
85% |
90% |
95% |
100% |
|

Here
is the living room and
kitchen of condo C5 in early April 2008.
|

Over
the last couple of weeks all of the
appliances and fixtures in C5 were installed.
|

These
are the pendant lights that hang above C5's breakfast bar.
|

C5's
master bathroom's countertops were recently installed.
|

The
marble surrounding the Jacuzzi
tub of condo C5 was also recently installed.
|

The
marble countertops in C5's
guest bathroom are now complete.
|

Here
is the stackable washer and dryer found in a
closet in C5's guest bathroom that was recently connected.
|

Some
of the mattresses that will be used on C5's
beds are presently stacked in the condo's guest bedroom.
|

This
is the view from C5's master bedroom
looking out onto the pool and grounds of The Phoenix.
|

Here
is the Caribbean view from C5's veranda
overlooking the main pool of The Phoenix.
|