C4 Construction Progress - March 2007


Milestone

Foundation

Walls

Roof

Windows & Doors

Paint & Tile

Finish Work

Complete

Completion Date

X

X

X

X

     

% Complete

20%

40%

60%

70%

80%

90%

100%





C4 is the second floor condo seen here on the right.







The living room of C4 was recently rough plastered.








The master bedroom opens directly onto the large veranda.









The recently rough plastered guest bedroom offers two large windows.








The drop ceiling above the veranda will soon be built.






The lovely Caribbean view from second floor condo C4.