C4 Construction Progress - September 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

X

X

X

Dec 07

Dec 07

Jan 08

Jan 08

% Complete

70%

75%

80%

85%

90%

95%

100%

The Phoenix Resort in Belize Condo C4 #1



C4's living room and kitchen were recently painted and tiled.



The Phoenix Resort in Belize Condo C4 #2


C4 offers a spectacular Caribbean view through
the palm trees found on the property The Phoenix.






The Phoenix Resort in Belize Condo C4 #3




Here is the recently painted and tiled master bedroom of C4.




The Phoenix Resort in Belize Condo C4 #4




The guest bedroom of C4 has also been painted and tiled.





The Phoenix Resort in Belize Condo C4 #5



The exterior of Building C will be painted
and tiled over the next couple of weeks.






The Phoenix Resort in Belize Condo C4 #6



In late September our crew began painting the exterior of Building C,
starting with the veranda of second floor condo C4, pictured at right.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6


The Phoenix Property 1




Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery