C3
Construction Progress - August 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
Aug
07 |
Oct
07 |
Dec
08 |
Jan
08 |
Feb
08 |
Feb
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

The
exterior walls of condo C3 condo have been finish plastered
|

Here
is Caribbean view from the veranda of C3.
|

Here is the finished veranda of C3 prior to being painted and
tiled.
|

Here is the view from the master bedroom of C3.
|

Here is the Caribbean view from C3's living room and kitchen.
|

The
drop ceilings in C3 are nearly complete.
The painting of C3 will begin later this month.
|