C3 Construction Progress - August 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

X

Aug 07

Oct 07

Dec 08

Jan 08

Feb 08

Feb 08

% Complete

70%

75%

80%

85%

90%

95%

100%

The Phoenix Resort in Belize Condo B1 #1



The exterior walls of condo C3 condo have been finish plastered


The Phoenix Resort in Belize Condo B1 #1



Here is Caribbean view from the veranda of C3.





The Phoenix Resort in Belize Condo B1 #1




Here is the finished veranda of C3 prior to being painted and tiled.





The Phoenix Resort in Belize Condo B1 #1




Here is the view from the master bedroom of C3.





The Phoenix Resort in Belize Condo B1 #1




Here is the Caribbean view from C3's living room and kitchen.





The Phoenix Resort in Belize Condo B1 #1



The drop ceilings in C3 are nearly complete.
The painting of C3 will begin later this month.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6



Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery