Construction Progress - September 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
Dec
07 |
Jan
08 |
Jan
08 |
Feb
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|