C2 Construction Progress - November 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

X

X

X

Jan 08

Feb 08

Feb 08

Mar 08

% Complete

70%

75%

80%

85%

90%

95%

100%


The Phoenix Resort in Belize Condo C2 #1



The exterior of Building C is now fully painted.


The Phoenix Resort in Belize Condo C2 #2


Here is the front veranda of condo C2
which was recently painted and tiled.




The Phoenix Resort in Belize Condo C2 #3




This is the Caribbean view from C2 overlooking the main pool.




The Phoenix Resort in Belize Condo C2 #4



Here is the recently tiled shower in C2's master bath
alongside where the condo's jacuzzi will be installed.






The Phoenix Resort in Belize Condo C2 #5




Here is the recently tiled shower in C2's guest bath.





The Phoenix Resort in Belize Condo C2 #6




This is one of the two owner's closets in condo C2.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6


The Phoenix Pools




Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery