C2
Construction Progress - February 2008
| Milestone |
Paint & Tile |
Kitchen
&
BTH Cabinets |
Appliances
& Fixtures |
Wood
Finish Work |
Furniture |
Complete |
|
Completion Date |
X |
X |
Apr
08 |
Apr
08 |
Apr
08 |
Apr
08 |
| %
Complete |
75% |
80% |
85% |
90% |
95% |
100% |
|

Here
is residential Building C in early February 2008.
Condo
C2 is the first floor two bedroom condo seen here on the right.
|

The
kitchen cabinets in condo C2 are nearly complete.
|

The
master bathroom cabinets are also finished. Above is a shelf
that will provide additional surface area below the bathroom's
mirror.
|

The
guest bathroom cabinets are also complete in condo C2.
|

Many
fixtures such as the Hunter ceiling
fans and recessed lights have been installed.
|

The
light fixtures above the area where mirrors will be
installed in the master and guest bathrooms have been added.
|

This
is the Caribbean view overlooking
the main pool of The Phoenix from condo C2.
|

Here
is a perspective on the construction of the
main pool from condo C2 in early February 2008.
|