C1 Construction Progress - July 2007


Milestone

Foundation

Walls

Roof

Windows & Doors

Paint & Tile

Finish Work

Complete

Completion Date

X

X

X

X

     

% Complete

20%

40%

60%

70%

80%

90%

100%

The Phoenix Resort in Belize Condo C1 #1



C1 offers a beautiful Caribbean view looking out over the grounds.


The Phoenix Resort in Belize Condo C2 #2


With the windows and doors up, our
crew is now working on the drop ceiling.




The Phoenix Resort in Belize Condo A12 #3



First we build the treated pine frame, and then we add the
recessed lights, plumbing infrastructure, and air conditioning system.




The Phoenix Resort in Belize Condo A12 #4



Our crew recently finished the rough plaster of
Building C's exterior and is now finish plastering the building.




The Phoenix Resort in Belize Condo A12 #5



Here is Building C's southeastern face
following the application of rough plaster.




The Phoenix Resort in Belize Condo A12 #6




Here is our crew rough plastering Building C's southwestern face.





A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6



Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery