C1
Construction Progress - July 2007
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
|
|
|
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

C1 offers a beautiful Caribbean view looking out over the grounds.
|

With
the windows and doors up, our
crew is now working on the drop ceiling.
|

First
we build the treated pine frame, and then we add the
recessed lights, plumbing infrastructure, and air conditioning
system.
|

Our
crew recently finished the rough plaster of
Building C's exterior and is now finish plastering the building.
|

Here
is Building C's southeastern face
following the application of rough plaster.
|

Here is our crew rough plastering Building C's southwestern face.
|