C1 Construction Progress - August 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

X

Sept 07

Oct 07

Jan 08

Feb 08

Feb 08

Mar 08

% Complete

70%

75%

80%

85%

90%

95%

100%

The Phoenix Resort in Belize Condo B1 #1



The exterior walls of condo C1 condo has been finish plastered.


The Phoenix Resort in Belize Condo B1 #1



Here is Caribbean view from the veranda of C1.






The Phoenix Resort in Belize Condo B1 #1




The drop ceiling above C1's living room and kitchen is complete.




The Phoenix Resort in Belize Condo B1 #1




Here is the Caribbean view from C1's living room and kitchen.




The Phoenix Resort in Belize Condo B1 #1




Here is the Caribbean view from C1's master bedroom.





The Phoenix Resort in Belize Condo B1 #1




The drop ceiling above the master bedroom is also complete.





The Phoenix Resort in Belize Condo B1 #1




The painting of the drop ceiling in the guest bedroom has begun.





The Phoenix Resort in Belize Condo B1 #1



The finish plastering of Building C is complete. Next
our crew will begin to tile the verandas and walkways.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6



Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery