C1
Construction Progress - August 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
Sept
07 |
Oct
07 |
Jan
08 |
Feb
08 |
Feb
08 |
Mar
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

The
exterior walls of condo C1 condo has been finish plastered.
|

Here is Caribbean view from the veranda of C1.
|

The
drop ceiling above C1's living room and kitchen is complete.
|

Here
is the Caribbean view from C1's living room and kitchen.
|

Here is the Caribbean view from C1's master bedroom.
|

The
drop ceiling above the master bedroom is also complete.
|

The painting of the drop ceiling in the guest bedroom has begun.
|

The
finish plastering of Building C is complete. Next
our crew will begin to tile the verandas and walkways.
|