C1 Construction Progress - September 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

X

X

X

Jan 08

Feb 08

Feb 08

Mar 08

% Complete

70%

75%

80%

85%

90%

95%

100%

The Phoenix Resort in Belize Condo C1 #1


Here is C1's Caribbean view, which also overlooks the
portion of the property where our main pool will be built.



The Phoenix Resort in Belize Condo C1 #2


With the finish plaster of the exterior of C1 now complete our
crew will begin painting and tiling the veranda in early October.






The Phoenix Resort in Belize Condo C1 #3



C1 is the first floor condo pictured here. The property of
The Phoenix will be in-filled to one step below C1's veranda.





The Phoenix Resort in Belize Condo C1 #4




Here is the recently painted and tiled master bedroom of C1.





The Phoenix Resort in Belize Condo C1 #5




Here is the painted and tiled guest bedroom of C1.





The Phoenix Resort in Belize Condo C1 #6



Here is the Caribbean view looking
out from the master bedroom of C1.






The Phoenix Resort in Belize Condo C1 #7



The living room and kitchen of C1
were also recently painted and tiled.






The Phoenix Resort in Belize Condo C1 #8



The exterior of Building C will be painted over next couple of
weeks with the cream colored acrocrete used on Buildings A & D.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6