B6 Construction Progress - September 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

Oct 07

Nov 07

Dec 07

Mar 08

Mar 08

Apr 08

Apr 08

% Complete

70%

75%

80%

85%

90%

95%

100%

The Phoenix Resort in Belize Condo B6 #1


B6 is the third floor three bedroom condo seen here. The
finish plastering of B6's exterior walls was recently completed.



The Phoenix Resort in Belize Condo B6 #2



B6 offers this amazing Caribbean view from its veranda.





The Phoenix Resort in Belize Condo B6 #3



Next our crew will install the condo's windows
and doors and begin work on the drop ceiling.





The Phoenix Resort in Belize Condo B6 #4



After the windows and doors are installed and
the drop ceiling is built, B6 will be painted and tiled.






The Phoenix Resort in Belize Condo B6 #5



The windows and doors for B6 are now in
Belize and will be installed in early October.






The Phoenix Resort in Belize Condo B6 #6



Building B's orientation means that there are unobstructed and
expansive Caribbean views from inside all six of its condos.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6


The Phoenix Property 1




Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery