Construction Progress - August 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
Sept
07 |
Oct
07 |
Nov
07 |
Feb
08 |
Feb
08 |
Mar
08 |
Mar
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

Here is the spacious wrap around veranda of third floor condo
B5.
|

This
is the beautiful Caribbean view from the veranda of B5.
|

The
kitchen and living room of B5 has been finish plastered.
|

B5's
master bedroom has also been finish plastered.
|

The
exterior walls of B5 were recently rough plastered.
|

Here is the master bedroom's amazing Caribbean view.
|

Here is the Caribbean view from the living room and kitchen of
B5.
|

Here is the southern face of Building B being rough plastered.
|