B5 Construction Progress - September 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

Oct 07

Nov 07

Nov 07

Mar 08

Mar 08

Apr 08

Apr 08

% Complete

70%

75%

80%

85%

90%

95%

100%

The Phoenix Resort in Belize Condo B5 #1


B5 is the third floor one bedroom condo seen here. The
finish plastering of B5's exterior walls was recently completed.



The Phoenix Resort in Belize Condo B5 #2



B5 offers this stunning Caribbean view from its veranda.





The Phoenix Resort in Belize Condo B5 #3



The windows and doors for B5 are now in
Belize and will be installed in early October.





The Phoenix Resort in Belize Condo B5 #4



After the windows and doors are installed, the drop
ceiling will be built, and then B5 will be painted and tiled.






The Phoenix Resort in Belize Condo B5 #5



The interior tile that will be used in B5 is pictured
here against the back wall of the condo's kitchen.






The Phoenix Resort in Belize Condo B5 #6



Here is the beautiful Caribbean view from the
rooftop above condo B5 in the late afternoon.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6


The Phoenix Property 1




Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery