B5
Construction Progress - November 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
Dec
07 |
Dec
07 |
Feb
08 |
Feb
08 |
Mar
08 |
Mar
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

B5
is the third floor three bedroom condo seen here at left.
|

The
veranda of B5 wraps around the condo's
offset living room and is 510 square feet in size.
|

This
is the beautiful Caribbean view from condo B5.
|

This
is a view of the main pool from B5.
|

The
drop ceiling is now complete in
B5 and the condo will soon be painted.
|
|