B4
Construction Progress - September 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
Oct
07 |
Nov
07 |
Nov
07 |
Mar
08 |
Mar
08 |
Apr
08 |
Apr
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

B4
is the second floor condo seen here at right.
|

The
plastering of B4's interior and exterior walls is now complete.
Next our crew will begin building the treated pine drop ceiling.
|

The
windows and doors for B4 are now in
Belize and will be installed in early October.
|

After
the drop ceiling is complete and the windows
and doors are installed B4 will be painted and then tiled.
|

The
interior tile that will be used in B4 is pictured
here against the back wall of the condo's kitchen.
|

Here
is the amazing Caribbean view
from condo B4 in the late afternoon.
|