Construction Progress - February 2007
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
Mar
07 |
|
|
|
|
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

Second floor condo B3 offers a terrific Caribbean view.
|

B3's interior walls were built in January 2007.
|

The crew is now
completing the exterior structural walls on B3's veranda.
|

The
crew will soon begin work on the
structural beams above B3's interior walls.
|

The roof of B3 is scheduled to be poured by the end of February.
|

The back hallway leading to B3 is taking shape.
|