Construction Progress - October 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
Nov
07 |
Nov
07 |
Feb
08 |
Feb
08 |
Mar
08 |
Mar
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

Here
is the beautiful Caribbean view from condo
B3, which also overlooks the pools of The Phoenix.
|

Here
is the view looking out from B3's living
room through its recently installed windows and doors.
|

The
drop ceiling in the living room will be completed
once the air conditioning duct work has been installed.
|

Here a crew member begins the tile work on B3's veranda.
|

Here
are the brand new windows
and doors of B3's master bedroom.
|

Following
the installation of the windows and doors,
our crew will next paint and tile the exterior of Building B.
|