B3
Construction Progress - April 2008
| Milestone |
Paint & Tile |
Kitchen
&
BTH Cabinets |
Appliances
& Fixtures |
Wood
Finish Work |
Furniture |
Complete |
|
Completion Date |
X |
May
08 |
May
08 |
May
08 |
May
08 |
May
08 |
| %
Complete |
75% |
80% |
85% |
90% |
95% |
100% |
|

Here
is the living room and
kitchen of condo B3 in early April 2008.
|

B3's
appliances recently arrived onsite and are ready to be
installed after the completion of the condo's kitchen cabinets.
|

Here
are the recently installed pendant lights that hang
above where the kitchen's breakfast bar will be installed.
|

This
is B3's Jacuzzi tub which can
be found in its spacious bathroom.
|

Many
of B3's fixtures have been installed
like the Kohler shower fixtures seen here.
|

This
is the view of the pools and grounds
from the master bedroom of condo B3.
|

Here
are the recently installed stainless
steel handrails of second floor condo B3.
|

Here
is a view of the lap pool and main pool
of The Phoenix as seen from B3's veranda.
|