Construction Progress - September 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
Oct
07 |
Nov
07 |
Dec
07 |
Mar
08 |
Mar
08 |
Apr
08 |
Apr
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

The
finish plaster of the exterior of B2 is complete.
|

Our
crew recently began building the treated pine
drop ceiling inside B2's living room and kitchen area.
|

Inside
the master bedroom the treated pine ceiling is
further along and light fixtures are now being installed.
|

Because
the foundation of Building B is raised over 6' above sea
level first floor condo B2 can provide this expansive Caribbean
view.
|

Our
crew here uses B2's spacious veranda to pile construction materials.
|

With
the completion of Building B's finish plaster all of the concrete
and plaster work for the condos of The Phoenix is now complete.
|