Construction Progress - August 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
Sept
07 |
Nov
07 |
Dec
07 |
Mar
08 |
Mar
08 |
Apr
08 |
Apr
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

Our
crew uses scaffolding in front of B1 to help apply
rough plaster across the eastern face of Building B.
|

Here
is the Caribbean view from the veranda of B1.
|

All
of the interior walls have been finish plastered.
|

B1's
exterior walls have been rough plastered
and its veranda drop ceiling is now complete.
|

Here
is the Caribbean view from the kitchen of B1.
|

Here
is the Caribbean view from the master bedroom of B1.
|

The
drop ceiling in the walkway
leading to B1 & B2 is almost complete.
|

Here
is the long & well lit hallway leading to condo B1.
|