B1
Construction Progress - September 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
Oct
07 |
Nov
07 |
Dec
07 |
Mar
08 |
Mar
08 |
Apr
08 |
Apr
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

The
finish plaster of the exterior of B1 is now complete.
|

With
the interior finish plaster also complete, our crew is now
building the treated pine drop ceiling and installing light fixtures.
|

Inside
the master bedroom lies the treated pine
that will be used to build the drop ceiling in the condo.
|

Because
the foundation of Building B is raised over 6' above sea
level first floor condo B1 can provide this beautiful Caribbean
view.
|

Here
some crew members complete the finish plastering of Building B.
|

All
of Building B is now finish plastered,
which is a significant milestone for the project.
|