Construction Progress - October 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
Nov
07 |
Dec
07 |
Mar
08 |
Mar
08 |
Apr
08 |
Apr
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

The
windows and doors of B1 were installed earlier this month.
|

Here is the view looking out from B1's living room.
|

The
plycem pictured at left will be installed in the drop
ceiling once the air conditioning duct work is completed.
|

At
center is B1's master closet and at
left is the entrance to the master bath.
|

The
window in the master bathroom has been
installed, as has the glass block in the wall of the shower.
|

With
the construction of the pools underway large
amounts of sand are piled high along the beachfront.
|