Construction Progress - May 2007
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
|
|
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

The
third floor of Building A will be
coated in acrocrete later this month.
|

Inside A9 the drop ceiling moves closer to completion. The air
conditioning ducting and recessed lights have all been installed.
|

A9
has a unique open design that connects all three rooms.
|

A9
offers beautiful Caribbean views through its
multiple Caribbean-facing bays of windows and doors.
|