Construction Progress - March 2007
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
|
|
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

A9 is the third floor condo pictured here. Four sets of
windows and doors provide access to the condo's spacious veranda.
|

The
rough plaster on the exterior walls of A9 is
now complete. The walls will soon be finish plastered.
|

Here
is the Caribbean view looking out through the
recently installed east facing set of windows and doors.
|

Construction
of the drop ceiling of A9 is presently underway.
|

This is where the kitchen will be built opposite the dining room.
|

The
exterior doors and windows were
installed throughout A9 in late March 2007.
|

A9's
unique floor plan connects all three rooms of
the condo via large openings in the bedrooms walls.
|

The
Long bay of windows and doors will bring
an abundance of natural light into condo A9.
|