Construction Progress - August 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
Oct
07 |
Oct
07 |
Nov
07 |
Nov
07 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

A9 is painted and tiled and woodworks will soon be installed.
|

Here is where the kitchen of A9 will be built.
|

This
is the amazing Caribbean view from A9's living room.
|

Here
is a view looking from the master bedroom
out towards the living room and the Caribbean.
|

The
master bedroom closets of A9 will soon be installed.
|

A9's wrap around veranda offers spectacular Caribbean views.
|