| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
May
07 |
June
07 |
Aug
07 |
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|