A8 Construction Progress - May 2007


Milestone

Foundation

Walls

Roof

Windows & Doors

Paint & Tile

Finish Work

Complete

Completion Date

X

X

X

X

May 07

June 07

Aug 07

% Complete

20%

40%

60%

70%

80%

90%

100%




Like the rest of Building A's second floor condos, we will soon
begin to cover A8's outer walls in a cream colored acrocrete.





During the past month we've completed the air conditioning
installation in A8 as well as begun installing the plycem.








Of the condos remaining for sale, A8 offers
the largest veranda at 770 square feet.







Here is the gorgeous Caribbean view from A8's veranda.







Here is the view looking through the openings in the
walls separating the second floor condos of Building A.








Here is the spacious and airy second floor hallway of Building A.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6


D1

D2

D3

D4

D5

D6



Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery