A8 Construction Progress - September 2007


Milestone

Windows
& Doors

Paint

Tile

Finish Work

Appliances
& Fixtures

Furniture

Complete

Completion Date

X

X

X

Jan 08

Feb 08

Mar 08

Apr 08

% Complete

70%

75%

80%

85%

90%

95%

100%

The Phoenix Resort in Belize Condo A8 #1


Here is the painted and tiled living room of A8. Next
our crew will begin installing recessed lights and fans.



The Phoenix Resort in Belize Condo A8 #2



A8 provides and expansive Caribbean view from its veranda.






The Phoenix Resort in Belize Condo A8 #3



Each room in condo A8 opens to its spacious
veranda, which is now fully painted and tiled.





The Phoenix Resort in Belize Condo A8 #4



Here is a framed view that the architecture
of The Phoenix creates from A8's veranda.






The Phoenix Resort in Belize Condo A8 #5



A8 is the only remaining second floor condo in Building A. It also
has the largest veranda (770 square feet) of any remaining condo.






The Phoenix Resort in Belize Condo A8 #6



With the exterior of Building A now fully painted and tiled, our
crew will focus on finishing the interiors of the Building's 12 condos.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6


The Phoenix Property 1




Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery