A8
Construction Progress - November 2007
| Milestone |
Windows
& Doors |
Paint |
Tile |
Finish
Work |
Appliances
& Fixtures |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
Feb 08 |
Feb
08 |
Mar
08 |
Apr
08 |
| %
Complete |
70% |
75% |
80% |
85% |
90% |
95% |
100% |
|

A8
is the second floor condo pictured here.
It is the last
remaining second floor two bedroom condo at The Phoenix.
|

A8's
floor plan includes a 770 square foot private veranda
that extends nearly 17' towards the pools and grounds.
|

Here
is November 2007 pool
construction viewed from A8's veranda.
|

This
is the expansive Caribbean view from A8.
|

The
living room of A8 presently contains woodoworks
being installed throughout Building A and Building C.
|

The
cabinets in the guest bathroom have been finished
and await the marble countertops and Kohler fixtures.
|

The
cabinets in the master bathroom have also been finished
and await the marble countertops and Kohler fixtures.
|

Here
is the view looking down the
beautiful back hallway that leads to condo A8.
|