A7 Construction Progress - May 2007


Milestone

Foundation

Walls

Roof

Windows & Doors

Paint & Tile

Finish Work

Complete

Completion Date

X

X

X

X

X

% Complete

20%

40%

60%

70%

80%

90%

100%




We will soon begin to cover A7's second
floor outer walls in a cream colored acrocrete





During the past month we've installed all of the air conditioning
ducting in A7. The drop ceiling is now ready for the plycem.







Like A5 & A6, the veranda of A7 offers a large,
private outdoor space in both the sun and the shade.







Here is the view looking through the openings in the
walls separating the second floor condos of Building A.








A7 offers a spectacular and expansive Caribbean view.








Here is the spacious and airy second floor hallway of Building A.




A1

A2

A3

A4

A5

A6

A7

A8

A9

A10

A11

A12


B1

B2

B3

B4

B5

B6

C1

C2

C3

C4

C5

C6


D1

D2

D3

D4

D5

D6



Construction Progress Chart

Construction History Chart

Construction Photo Gallery

Main Photo Gallery