Construction Progress - March 2007
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
|
|
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

A7 is the second floor condo pictured here. Three sets of
windows and doors provide access to the condo's spacious veranda.
|

The
exterior walls of A7 will soon be finish plastered.
|

Because
of the layout of Building A each condo
offers an unobstructed and expansive Caribbean view.
|

The 770 square foot veranda extends nearly 17' towards the Caribbean.
|

The
floor tile that will soon be used
in A7 is stacked in the living room.
|

This
is the Caribbean view from A7's master bedroom.
|

The
recessed lights have been installed in A7 and soon the air
conditioning systems will be built into the treated pine framework.
|

The
openings in the privacy walls allow for framed vistas like this.
|