Construction Progress - February 2008
| Milestone |
Paint & Tile |
Kitchen
&
BTH Cabinets |
Appliances
& Fixtures |
Wood
Finish Work |
Furniture |
Complete |
|
Completion Date |
X |
X |
X |
Mar
08 |
Mar
08 |
Mar
08 |
| %
Complete |
75% |
80% |
85% |
90% |
95% |
100% |
|

The
GE stainless steel appliances of
condo A7 were recently installed.
|

This
is the living room of condo A7 in mid February 2008.
The
wood seen at right will soon be installed throughout the condo.
|

This
is the view looking out through the
large windows and doors of A7's guest bedroom.
|

This
is the view looking out through the
large windows and doors of A7's master bedroom.
|

The
guest bathroom of A7 features Belizean
hardwood cabinetry, marble countertops, and Kohler fixtures.
|

The cabinets, marble countertops, and fixtures of
A7's master bathroom were all recently installed.
|

A7's
Jacuzzi tub was recently set and
soon the Kohler fixtures will be installed.
|

This
is the amazingly large private veranda of condo A7.
|

This
is the view from condo A7 looking out
over the lap pool and main pool of The Phoenix.
|

All
of the condos of The Phoenix
offer expansive Caribbean views.
|

Here
is the lap pool of The Phoenix in mid February 2008.
|

The
stainless steel handrails of
condo A7 will be installed next month.
|