A6
Construction Progress - March 2007
| Milestone |
Foundation |
Walls |
Roof |
Windows
& Doors |
Paint
& Tile |
Finish
Work |
Complete |
|
Completion Date |
X |
X |
X |
X |
X |
|
|
| %
Complete |
20% |
40% |
60% |
70% |
80% |
90% |
100% |
|

A6 is the second floor condo pictured here. Three sets of
windows and doors provide access to the condo's spacious veranda.
|

The
exterior of A6 will soon be finish plastered.
|

The
floor tile that will soon be used in A6 is stacked in the living
room.
|

Our
crew is nearing completion of the condo's drop ceiling.
|

The
770 square foot veranda extends
nearly 17' towards the Caribbean.
|

The
privacy walls separating A6 & A5
offers this framed Caribbean view.
|

A6's
Caribbean views are magnificent.
|

Here
is the long hallway that spans the length of condo A6.
|